CCR Rule Compliance Data and Information

Peg’s Hill Landfill

 

Reports

                       

Location Restrictions 257.107(e)

Placement above the uppermost aquifer

Seismic impact zones

Unstable areas

Fault areas

Wetlands

Pegs Hill_Landfill_20170727_Location Restriction & Design Demonstration Report

 

Design Criteria

Pre-Construction design and construction certifications for new CCR Landfills and Lateral Expansions 257.107 (f) (1)0

Post-Construction certifications for new CCR Landfills and Lateral Expansions 257.107 (f) (2)

Pegs Hill_Landfill_20230922_Post-Construction Design and Construction Certifications for Phase 1A

Pegs Hill_Landfill_20231116_Post-Construction Design and Construction Certifications for Phase 1B

 

Operating Criteria

Fugitive Dust Plan 257.107 (g) (1)

Spurlock_20230922_Fugitive Dust Control Plan Rev 2

Annual Fugitive Dust Report 257.107 (g) (2)

Spurlock_20231129_Annual Fugitive Dust Report

Initial and Periodic Run-on Run-off Control System Plan (Landfills) 257.107 (g) (3)

Pegs Hill_Landfill_20230922_Periodic Run-On and Run-Off Plan

Corrective Measures to respond to a deficiency or release 257.107 (g) (6)

Initial and Periodic Annual Inspection Landfills 257.107 (g) (7)

 

Groundwater

Annual Groundwater Monitoring and Corrective Action Report 257.107 (h) (1)  

               Peg's Hill_Landfill_20200131_Annual GWMCA Report_Rev 01

               Peg's Hill_Landfill_20210131_Annual GWMCA Report_Rev 01

               Peg's Hill_Landfill_20220131_Annual GWMCA Report_Rev 01

               Peg's Hill_Landfill_20230131_Annual GWMCA Report

Peg's Hill_Landfill_20240131_Annual GWMCA Report

Groundwater Monitoring System Design and Construction Certification 257.107 (h) (2)  

               Peg's Hill_Landfill_20210524_Groundwater Monitoring System Certification

Certification of the Selection of Statistical Method (Groundwater Monitoring Plan) 257.107 (h) (3)  

               Peg's Hill_Landfill_20191017_Statistical Method Selection & Certification

               Pegs Hill_Landfill_20230922_Statistical Method Selection & Certification

Notification that an assessment monitoring program has been established 257.107 (h) (4)  

Notification that the CCR Unit is returning to a detection monitoring program 257.107 (h) (5)  

Notification that a constituent level is statistically significant 257.107 (h) (6)  

Notification that an assessment of corrective measures has been initiated 257.107 (h) (7)  

Assessment of corrective measures 257.107 (h) (8)  

Semi-annual reports describing remedy selection 257.107 (h) (9)   

Notification of remedy completion 257.107 (h) (10) 

 

Closure/Post Closure

Written Closure Plan 257.107 (i) (4)

Pegs Hill_Landfill_20230922_Closure Plan

Demonstration for time extension to Initiate Closure 257.107 (i) (5)  

Demonstration for time extension to Complete Closure 257.107 (i) (6)  

Notification of Intent to Initiate Closure 257.107(i) (7)

Notification of Closure Completion 257.107 (i) (8)  

Notification of Recording a Notation on the Deed 257.107 (i) (9)  

Notification of Intent to comply with Alternative Closure requirements 257.107 (i) (10)  

Annual progress reports under the alternative closure requirements 257.107 (i) (11)  

Written post closure plan and any amendment of the plan 257.107 (i) (12)  

Pegs Hill_Landfill_20230922_Post Closure Plan

Notification of Post-Closure Care Completion 257.107 (i) (13)